Saray Hydroelectric Power Plant

Saray Hydroelectric Power Plant

Saray HEPP Generation Facility in Rize province will be commissioned June 2014.

Key Project Quantities:

  • Yearly Production: 60.000.000 kWh
  • TransferType: 4000 m Horseshoe
  • Water Inlet Structure: Directly taken from Incirli
  • Turbine: 3 Vertical Full Kaplan
  • Net Fall: 29,7 m max., 24,8 m min.
  • Flow Rate: 62 m³/s
  • Water Intakes And Settling Basin (3 nos 4.00x4.20 m vertical inlet gate & 3 nos 4.00x3.60 m vertical sluiceway gate)
  • Water Transmission Line (L=120 m, D=5.30 m)
  • Water Tunnel (L=3743 m, D=5.30 m horse-shoe lined tunnel)
  • Penstock (L=50.80 m, D=4.50 m circular section, embedded in reinforced concrete underground)
  • Surge Tank (D=21 m, H=18 m circular section, steel lined reinforced concrete) (Underground)
  • Power Plant (2 units, each 6.75 MW, total installed capacity is 13.50 MW, 60 GWh/year energy production)

Project Details

Share This

  • Project TypeDesign – Build - Operate
  • Project LocationTrabzon, TURKEY
  • OwnerMertler Energy A.Ş.
  • Project StartSeptember 2011
  • Project EndApril 2014
  • Contract Value31,952,500.00 $